GAA 2024 OO-224L00204

CONSTRUCTION OF EARTH DIKE ALONG LOCUTAN RIVER (GOING TO TUGANAY RIVER) PHASE 1, CARMEN, DAVAO DEL NORTE

CONSTRUCTION OF EARTH DIKE ALONG LOCUTAN RIVER (GOING TO TUGANAY RIVER) PHASE 1, CARMEN, DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱185,917,976.93. Status: Past target date (DPWH On-Going). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱185,917,976.93

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2024

Target End

March 31, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.