Roads17HH0056

CONCRETING OF BRGY. LAHUG FARM TO MARKET ROAD, BRGY. LAHUG, CEBU CITY

CONCRETING OF BRGY. LAHUG FARM TO MARKET ROAD, BRGY. LAHUG, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱3,778,346.41. Status: Reported complete (DPWH). Contractor on record: WORLDWIDE BUILDERS. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Mitigation Structures along Lahug River, Brgy. Lahug, Cebu City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0022755

₱2,108,129.00 · FY2017

Released to Philippine Air For ( Air Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

256 projects · ₱2.1B total · 4 flags

Other projects by this contractor

Construction of Dike along Kabalaasnan River, Dumanjug, Cebu

DUMANJUG (CEBU), CEBU, Region VII

2023₱96.5M
Reported complete (DPWH)

Construction of River Retaining Wall Structure at Sitio Upper Talayong, Barangay Tupas, Ronda, Cebu (Upstream)

RONDA (CEBU), CEBU, Region VII

2023₱96.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF RIVER CHANNEL IMPROVEMENT ALONG SITIO UPPER TALAYONG - SITIO LOWER T

Cebu 7th DEO, Region VII

2023₱75.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE - CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION/FLOOD MITIGATION STRUCTURE, BARANGAY PANALIPAN, CATMON, CEBU

Cebu 5th DEO, Region VII

2021₱71.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL DIKE AT BARANGAY KABALAASNAN (DOWNST

Cebu 7th DEO, Region VII

2024₱70.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, PUROK LUBE, BARANGAY KABALAASNAN (DOWNSTR

Cebu 7th DEO, Region VII

2025₱70.9M
Past target date (DPWH On-Going)
View all 256 projects →

4. Implementation

Contract Amount

₱3,778,346.41

Progress

Reported complete (DPWH)

Start Date

September 4, 2017

Target End

December 17, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.