Rehabilitation / Major Repair of Flood Control Structure22OD0213

Rehabilitation of Maligaya Creek, Barangay 118 and 120, Caloocan City

Rehabilitation of Maligaya Creek, Barangay 118 and 120, Caloocan City is a DPWH-tracked public work in CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region. Reported contract value: ₱38,405,318.07. Status: Reported complete (DPWH). Contractor on record: J SIMEON CONST. Figures trace to sumbong.

CALOOCAN CITY (METROPOLITAN MANILA), CALOOCAN CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Maintenance and Rehabilitation of Flood Control Structure along Ilugin River, Pasig City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002758

₱421,090,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001739

₱150,239,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003179

₱1,355,100,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003051

₱37,450,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001635

₱4,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001969

₱145,188,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱38,405,318.07

Progress

Reported complete (DPWH)

Start Date

March 22, 2022

Target End

January 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.