Construction of Slope Protection Structure24CJ0097

Construction of Slope Protection along Camiling River, Left Bank, Anoling 1st to Pao 2nd Section (Segment D), Camiling River

Construction of Slope Protection along Camiling River, Left Bank, Anoling 1st to Pao 2nd Section (Segment D), Camiling River is a DPWH-tracked public work in CAMILING (TARLAC), TARLAC, Region III. Reported contract value: ₱41,151,460.00. Status: Reported complete (DPWH). Contractor on record: GJE BUILDERS CORP FORMERLY: GJE BUILDERS. Figures trace to sumbong.

CAMILING (TARLAC), TARLAC, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tarlac River - O'Donnell River Control, Balanti - Armenia Section ( Segment N ) , Tarlac City, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-24-0018106

₱90,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008257

₱1,904,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008259

₱176,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱41,151,460.00

Progress

Reported complete (DPWH)

Start Date

March 11, 2024

Target End

August 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.