Flood Control and Drainage18CA0029

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL PROJECT IN ORANI RIVER, APOLLO SECTION, ORANI, BATAAN

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL PROJECT IN ORANI RIVER, APOLLO SECTION, ORANI, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱18,360,296.58. Status: Reported complete (DPWH). Contractor on record: TRIPLE 8 CONST. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0014605 · · release to the district office, not itemized per project

    Possible match · score 0.79

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱17,071,405 · TRIPLE 8 CONST. & SUPPLY .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2013-01-21 → 2025-02-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Bataan

Based on the coordinates published with the DPWH record and NOAH file Bataan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL PROJECT IN ORANI RIVER, APOLLO SECTION, ORANI, BATAAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems, Talisay River, Balut Section, Pilar, Bataan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014605

₱0.00 · FY2018

Released to Division of Bataan (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Contractor

276 projects · ₱13.4B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF REVETMENT ALONG MARIBLO CREEK, STA. 0+010.000 TO STA. 0+524.458 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱195.0M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADSBACOOR - DASMARIÑAS NATIONAL RD. - K0028 + 215 - K0028 + 404, K0029 + 204 - K0029 + 780, K0029 + 822 - K0030 + 675, K0030 + 716 - K0030 + 1002, K0031 + 015 - K0031 + 609

Region IV-A, Region IV-A

2023₱154.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION OF CAMP AGUINALDO ROAD NETWORK, PACKAGE A, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT ALONG DARIO CREEK, STA. 0+020.000 TO STA. 0+351.894 (LEFT AND RIGHT RIVER BANK), QUEZON CITY

Flood Control Management Cluster, Central Office

2021₱135.7M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES-CONSTRUCTION OF OPEN UNIVERSITY SYSTEM BUILDING IN POLYTECHNIC UNIVERSITY OF THE PHILIPPINES (PUP) PHASE II AT PUP A. MABINI CAMPUS, STA. MESA, MANILA

South Manila DEO, National Capital Region

2023₱111.0M
Reported complete (DPWH)

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, FLOOD CONTROL AND DRAINAGE, FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, BRGY. BUHAY NA TUBIG, PHASE IV, IMUS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2019₱99.0M
Reported complete (DPWH)
View all 276 projects →

4. Implementation

Contract Amount

₱18,360,296.58

Progress

Reported complete (DPWH)

Start Date

March 26, 2018

Target End

November 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.