Construction of Flood Mitigation Structure24CC0181

Constructionmprovement of Flood Mitigation Structure at Carillo, Hagonoy, Bulacan

Constructionmprovement of Flood Mitigation Structure at Carillo, Hagonoy, Bulacan is a DPWH-tracked public work in HAGONOY (BULACAN), BULACAN, Region III. Reported contract value: ₱77,199,909.53. Status: Reported complete (DPWH). Contractor on record: 11-16 CONST. Figures trace to sumbong.

HAGONOY (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Madlum River, Brgy. Masalipit, San Miguel, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱77,199,909.53

Progress

Reported complete (DPWH)

Start Date

February 28, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.