Construction of Flood Mitigation Structure22CC0148

Construction of Bulihan-Longos Creek, Malolos City, Bulacan

Construction of Bulihan-Longos Creek, Malolos City, Bulacan is a DPWH-tracked public work in CITY OF MALOLOS (CAPITAL) (BULACAN), BULACAN, Region III. Reported contract value: ₱48,998,604.86. Status: Reported complete (DPWH). Contractor on record: FRAMECON BUILDERS. Figures trace to sumbong.

CITY OF MALOLOS (CAPITAL) (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Strucrure (Slope Protection), Brgy. Bahay Pare, Meycauayan City, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002958

₱2,583,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002898

₱71,500,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0000929

₱84,820.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,998,604.86

Progress

Reported complete (DPWH)

Start Date

February 18, 2022

Target End

February 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.