Buildings and Facilities23DE0184

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING (HEALTH CLINIC) IN BARANGAY MANGHINAO PROPER, BAUAN,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, COMPLETION OF MULTI-PURPOSE BUILDING (HEALTH CLINIC) IN BARANGAY MANGHINAO PROPER, BAUAN, is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱9,359,535.00. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: RGE CONST AND SUPPLY INC FORMERLY:R G EVANGELISTA CONST AND SUPPLY. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱42,648,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure at Barangay Bolbok, Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

68 projects · ₱374.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD, BRGY. TAYSAN-BRGY. PALANCA, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱24.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, GULIBAY, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, MUNICIPALITY OF SAN PASCUAL, BATANGAS

Batangas 2nd DEO, Region IV-A

2022₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS LOCATED AT SAN MIGUEL (TANGKE ROAD) STO.

Batangas 3rd DEO, Region IV-A

2025₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY INICBULAN, B

Batangas 2nd DEO, Region IV-A

2024₱14.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FOUR (4) STOREY FOUR (4) WORKSHOP BUILDING AT TAYSAN NHS, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2017₱13.4M
Reported complete (DPWH)
View all 68 projects →

4. Implementation

Contract Amount

₱9,359,535.00

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

June 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.