Construction of Drainage Structure24DO0009

Construction of Flood Control Structure in Barangay Ampid - 1, San Mateo, Rizal

Construction of Flood Control Structure in Barangay Ampid - 1, San Mateo, Rizal is a DPWH-tracked public work in SAN MATEO (RIZAL), RIZAL, Region IV-A. Reported contract value: ₱4,950,000.00. Status: Reported complete (DPWH). Contractor on record: C E M CONST INC. Figures trace to sumbong.

SAN MATEO (RIZAL), RIZAL, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Barangay Ampid - 1, San Mateo, Rizal
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004412

₱412,074.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0000922

₱284,988.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008436

₱1,416,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008437

₱131,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0004413

₱21,509.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0017824

₱135,627.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

123 projects · ₱1.7B total · 1 flags

4. Implementation

Contract Amount

₱4,950,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

June 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.