Buildings and Facilities25HF0071

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF HALL OF JUSTICE (PHASE III), BARANGAY POBLACION, BARILI, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF HALL OF JUSTICE (PHASE III), BARANGAY POBLACION, BARILI, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱31,834,787.25. Status: Past target date (DPWH On-Going). Contractor on record: JANUARY BUILDERS. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tagamakan CIS, Asturias, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

254 projects · ₱1.9B total · 3 flags

4. Implementation

Contract Amount

₱31,834,787.25

Progress

Past target date (DPWH On-Going)

Start Date

April 2, 2025

Target End

October 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.