Buildings and Facilities15LG0210

CONSTRUCTION OF MPB , DORECO COMPOUND, MATI CITY, DAVAO ORIENTAL

CONSTRUCTION OF MPB , DORECO COMPOUND, MATI CITY, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱2,964,387.50. Status: Reported complete (DPWH). Contractor on record: FIVE MASSIVE INFRA. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱41,026,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bilawan Flood Control, Mati City, protecting President Diosdado P. Macapagal National Highway, Davao Oriental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0033564

₱19,191.00 · FY2016

Released to Eastern Visayas Centers for Health Development Fun (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

209 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱2,964,387.50

Progress

Reported complete (DPWH)

Start Date

October 10, 2016

Target End

December 8, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.