Flood Control and Drainage21IJ0059

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JIBATANG RIVER (UPSTREAM), BRGY. OQUENDO (PUROK 2), CALBAYOG CITY, SAMAR

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JIBATANG RIVER (UPSTREAM), BRGY. OQUENDO (PUROK 2), CALBAYOG CITY, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱39,012,500.78. Status: Reported complete (DPWH). Contractor on record: ND CARANZO BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pe±a River (Upstream), Brgy. Pe±a, Calbayog City, Samar
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Samar 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

85 projects · ₱758.2M total · 0 flags

4. Implementation

Contract Amount

₱39,012,500.78

Progress

Reported complete (DPWH)

Start Date

February 4, 2021

Target End

November 26, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.