Buildings and Facilities23KD0037

CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY NAZARETH, CAGAYAN DE ORO CITY

CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY NAZARETH, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Cagayan de Oro City 2nd DEO, Region X. Reported contract value: ₱9,600,798.98. Status: Reported complete (DPWH). Contractor on record: AKC BUILDERS. Figures trace to dpwh.

Cagayan de Oro City 2nd DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱10,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-03-11 → 2020-03-11

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/ Slope Protection, Barangay FS Catanico, Cagayan de Oro City, Misamis Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cagayan de Oro City 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,600,798.98

Progress

Reported complete (DPWH)

Start Date

April 1, 2023

Target End

November 26, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.