Roads20HJ0062

NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BRDY), K0066+940-K0067+500, K0068+000-K0068+734, K0071+000-K0071+502, K0087+350-K0067+450, K0087+600-K0087+700, DUMAGUETE NORTH ROAD

NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS DUMAGUETE NORTH RD (JCT BAIS-KABANKALAN-NEGROS OCC BRDY), K0066+940-K0067+500, K0068+000-K0068+734, K0071+000-K0071+502, K0087+350-K0067+450, K0087+600-K0087+700, DUMAGUETE NORTH ROAD is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱16,958,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Jimalalud River at North Pob. Jimalalud, Negros Oriental
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Negros Oriental 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Project

₱46,059,986.08 · SYNDTITE CONSTRUCTION

Contractor

B

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

December 8, 2020

Target End

October 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.