Roads18GF0084

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - GUIMBAL - IGBARAS - TUBUNGAN - LEON ROAD, TUBUNGAN, ILOILO (K0059+588 - K0059+643, K0059+836 - K0059+884, K0060+358 - K0060+369)

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - GUIMBAL - IGBARAS - TUBUNGAN - LEON ROAD, TUBUNGAN, ILOILO (K0059+588 - K0059+643, K0059+836 - K0059+884, K0060+358 - K0060+369) is a DPWH-tracked public work in Iloilo 1st DEO, Region VI. Reported contract value: ₱67,660,525.22. Status: Reported complete (DPWH). Contractor on record: ALPHA. Figures trace to dpwh.

Iloilo 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Guimbal Flood Control Project, Mancillas, Guimbal, Iloilo
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0033578

₱0.00 · FY2018

Released to Division of Ilocos Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

831 projects · ₱32.1B total · 0 flags

4. Implementation

Contract Amount

₱67,660,525.22

Progress

Reported complete (DPWH)

Start Date

July 2, 2018

Target End

April 27, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.