ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY MASARAWAG (PU
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY MASARAWAG (PU is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱47,042,258.97. Status: Past target date (DPWH On-Going). Contractor on record: WCS CONST INC. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost