Buildings and Facilities19LD0086

REHABILITATION OF MULTIPURPOSE BUILDING (GYMNASIUM), GUIHING, HAGONOY, DAVAO DEL SUR

REHABILITATION OF MULTIPURPOSE BUILDING (GYMNASIUM), GUIHING, HAGONOY, DAVAO DEL SUR is a DPWH-tracked public work in Davao del Sur DEO, Region XI. Reported contract value: ₱2,970,000.00. Status: Reported complete (DPWH). Contractor on record: R C MELGAZO BUILDERS. Figures trace to dpwh.

Davao del Sur DEO, Region XI
Region: Region XI

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-BMB-E-19-0003090 · ₱180,662 · release to the district office, not itemized per project

    Possible match · score 0.68

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19LD0086 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-08-22 → 2025-09-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF MULTIPURPOSE BUILDING (GYMNASIUM), GUIHING, HAGONOY, DAVAO DEL SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-19-0003090

₱180,662.00 · FY2019

Released to Regional Field Unit - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,970,000.00

Progress

Reported complete (DPWH)

Start Date

July 5, 2019

Target End

October 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.