Roads18CG0017

CONSTRUCTION/IMPROVEMENT OF MAPALAD-CANDATING ROAD, ARAYAT, PAMPANGA, ARAYAT, PAMPANGA

CONSTRUCTION/IMPROVEMENT OF MAPALAD-CANDATING ROAD, ARAYAT, PAMPANGA, ARAYAT, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱13,678,401.00. Status: Reported complete (DPWH). Contractor on record: B P CRUZ BUILDERS AND TRADING. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Slope Protection along Pampanga River, Candating Section, Arayat, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0014497

₱0.00 · FY2018

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

18CG0017 - Construction/ Improvement of Mapalad –

₱13,678,402.00 · B.P. CRUZ BUILDERS AND TRADING

Contractor

35 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG); CONSTRUCTION/IMPROVEMENT/REHABILITATION OF MULTIPURPOSE BUILDING IN ANGELES CITY, PAMPANGA

Pampanga 3rd DEO, Region III

2023₱72.4M
Reported complete (DPWH)
No sat.

Rehabilitation of Existing Dike along Lucung River (San Rafael Section, Right Bank), Sta. 8+585 to Sta. 8+985, Bamban, Tarlac

BAMBAN (TARLAC), TARLAC, Region III

2022₱57.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM; CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONST OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES FOUNDATION ALONG ABACAN RIVER, BRGY PULUNG MARAGUL, ANGELES CITY, PAMPANGA-STA 1+800-STA 2+550

Pampanga 3rd DEO, Region III

2022₱55.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ZAMBALES NAVAL HOSPITAL, NAVAL STATION LEOVIGILDO GANTIOQUI (NSLG), SAN ANTONIO, ZAMBALES

Zambales 1st DEO, Region III

2022₱49.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM; CONST./REPAIR/REHAB/IMPROVEMENT OF VARIOUS INFRA INCLUDING LOCAL PROJECTS; FLOOD CONTROL AND DRAINAGE; DRAINAGE/SLOPE PROTECTION WORKS; CONST. OF SLOPE PROTECTION ALONG QUITANGIL CREEK, BRGY. LA PAZ TO BRGY SAN NICOLAS, MAGALANG,PAMPANGA

Pampanga 3rd DEO, Region III

2021₱49.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM;CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS;REHAB OF SLOPE PTOTECTION WITH STEEL SHEET PILES FOUNDATION ALONG ABACAN RIVER,BRGY PANDAN TO BRGY CAPAYA, ANGELES CITY PAMPANGA

Pampanga 3rd DEO, Region III

2020₱48.9M
Reported complete (DPWH)
View all 35 projects →

4. Implementation

Contract Amount

₱13,678,401.00

Progress

Reported complete (DPWH)

Start Date

March 6, 2018

Target End

July 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.