Buildings and Facilities18KL0130

COMPLETION OF SCHOOL BUILDING PROJECT BATCH 1, 4 STOREY 8 CLASSROOMS (2 SCIENCE LAB, 2 ICT LAB), OPOL NSTS, OPOL, MISAMIS ORIENTAL

COMPLETION OF SCHOOL BUILDING PROJECT BATCH 1, 4 STOREY 8 CLASSROOMS (2 SCIENCE LAB, 2 ICT LAB), OPOL NSTS, OPOL, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱3,710,664.00. Status: Reported complete (DPWH). Contractor on record: CAGALAWAN ENT. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Iponan Flood Control Projects - Construction of Dike Downstream of Iponan Bridge III (Phase I), Barra, Opol, Misamis Oriental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-18-0015091

₱0.00 · FY2018

Released to Misamis Oriental 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

452 projects · ₱4.0B total · 0 flags

4. Implementation

Contract Amount

₱3,710,664.00

Progress

Reported complete (DPWH)

Start Date

November 14, 2018

Target End

January 12, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.