Roads22AI0007

CONSTRUCTION OF ROAD, BARANGAY SUGCONG, CITY OF URDANETA, PANGASINAN

CONSTRUCTION OF ROAD, BARANGAY SUGCONG, CITY OF URDANETA, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱4,946,365.99. Status: Reported complete (DPWH). Contractor on record: W J P CONST AND SUPPLY. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,875,134 · W.J.P CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-09-11 → 2025-02-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ROAD, BARANGAY SUGCONG, CITY OF URDANETA, PANGASINAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bued River, Barangay Amagbagan-Tara-Tara, Sison, Pangasinan (Package 1)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Pangasinan 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,946,365.99

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

April 9, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.