Roads21P00087

LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONSTRUCTION / IMPROVEMENT OF DADA - BEYENG - KAYAPA ROAD, DADA, BEYENG AND KAYAPA, BAKUN, BENGU

LOCAL PROGRAM: CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONSTRUCTION / IMPROVEMENT OF DADA - BEYENG - KAYAPA ROAD, DADA, BEYENG AND KAYAPA, BAKUN, BENGU is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: DJY CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

104 projects · ₱7.2B total · 3 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BEYENG - TACADANG ROADBAKUN & KIBUNGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱198.0M
Reported complete (DPWH)
No sat.

KIANGAN - TINOC - BUGUIAS RD - KO355+520 - KO355+668TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2022₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0308+979 - KO309+08

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD, ABINUAN - NATTUM - ALIMIT (MAYOYAO), BARANGAY BOLIWONG, LAGAWE, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2024₱191.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PINTO STA.31+800 - STA. 33+650 (L/S) ALFONSO LISTA, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2025₱190.0M
Past target date (DPWH On-Going)
View all 104 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

January 7, 2022

Target End

December 20, 2022

5. Audit