Flood Control and Drainage25PL0035

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY NEW TANGLAG (B/S),

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY NEW TANGLAG (B/S), is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱28,948,199.25. Status: Past target date (DPWH On-Going). Contractor on record: HKBT CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Mananig River at Cullayanan, Barangay Junction, Pinukpuk, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lower Kalinga DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

14 projects · ₱166.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL ALONG CHICO RIV

Upper Kalinga DEO, Cordillera Administrative Region

2024₱29.4M
Reported complete (DPWH)
No sat.

(1) RECONSTRUCTION OF THE BAMBOO FOOTBRIDGE AT SAMANG CREEK, SAKKI-ING FOOTBRIDGE AND KALIMANGOWAN FOOTBRIDGE, SITIO PAYAO, BRGY. LOWER UMA, LUBUAGAN, KALINGA(2) RECONSTRUCTION OF SUKLAP SUSPENSION FOOTBRIDGE, SUKLAP, BRGY. TANGLAG, LUBUAGAN KALINGA(3

Cordillera Administrative Region, Cordillera Administrative Region

2020₱19.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALO

Lower Kalinga DEO, Cordillera Administrative Region

2025₱19.3M
Past target date (DPWH On-Going)
No sat.

Construction of Flood Control (liglig GIIPO) along Chico River, Sta. 169 + 650 - Sta. 169 + 950 (RS), Barangay Tanglag, Lubuagan, Kalinga

LUBUAGAN (KALINGA), KALINGA, Cordillera Administrative Region

2023₱16.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAINWATER COLLECTOR SYSTEM - WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SYSTEM, BARANGAY COMMUNITY WATERWORKS IN OLATA, BARANGAY MABILONG

Upper Kalinga DEO, Cordillera Administrative Region

2022₱14.7M
Reported complete (DPWH)
No sat.

Construction of Flood Control at Kabiggen, Sta. 180 + 690 - Sta. 180 + 850 (RS), Western Uma, Lubuagan, Kalinga

LUBUAGAN (KALINGA), KALINGA, Cordillera Administrative Region

2023₱9.8M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱28,948,199.25

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

December 1, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.