Buildings and Facilities20OB0410

CONSTRUCTION (COMPLETION) OF BARANGAY CONCEPCION UNO MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT BRGY. CONCEPCION UNO, MARIKINA CITY

CONSTRUCTION (COMPLETION) OF BARANGAY CONCEPCION UNO MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT BRGY. CONCEPCION UNO, MARIKINA CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱6,720,529.70. Status: Reported complete (DPWH). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sapang Baho, Marikina City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Metro Manila 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

217 projects · ₱8.6B total · 22 flags

Other projects by this contractor

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Mulawin, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱236.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
View all 217 projects →

4. Implementation

Contract Amount

₱6,720,529.70

Progress

Reported complete (DPWH)

Start Date

November 25, 2020

Target End

February 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.