Buildings and Facilities21CC0171

PACKAGE 6 - CONST. OF MULTI-PURPOSE BUILDING, LOGIA NG CACARONG RESETTLEMENT, REAL DE CACARONG, CONST. OF MULTI-PURPOSE BUILDING, BAKA-BAKAHAN ES, BAKA-BAKAHAN & CONST. (COMPLETION) OF MULTI-PURPOSE BUILDING MASAGANA ES, MASAGANA, PANDI, BULACAN

PACKAGE 6 - CONST. OF MULTI-PURPOSE BUILDING, LOGIA NG CACARONG RESETTLEMENT, REAL DE CACARONG, CONST. OF MULTI-PURPOSE BUILDING, BAKA-BAKAHAN ES, BAKA-BAKAHAN & CONST. (COMPLETION) OF MULTI-PURPOSE BUILDING MASAGANA ES, MASAGANA, PANDI, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱2,938,580.23. Status: Reported complete (DPWH). Contractor on record: SYMS CONST TRADING. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (School Improvement, Concreting of School Grounds), St. Martha ES, Batia, Bocaue, Bulacan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bulacan 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Package 6 Construction of Multi-Purpose Building,

₱2,938,580.23 · SYMS CONSTRUCTION TRADING

4. Implementation

Contract Amount

₱2,938,580.23

Progress

Reported complete (DPWH)

Start Date

March 1, 2021

Target End

June 28, 2021

5. Audit