Flood Control and Drainage20MF0017

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE: CONSTRUCTION OF FLOOD CONTROL OF BANGA RIVER ALONG RAJAH MUDA, TACURONG CITY, SULTAN KUDARAT

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE: CONSTRUCTION OF FLOOD CONTROL OF BANGA RIVER ALONG RAJAH MUDA, TACURONG CITY, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱46,451,465.16. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood control of Banga River along Rajah Muda, Tacurong, Sultan Kudarat
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Sultan Kudarat 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,112 projects · ₱59.5B total · 113 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD AND CAUSEWAY, BRGY. CAMBAJAO-BRGY. ALIBAGON, CAJIDIOCAN, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱297.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG CARMEN PORT, SAN AGUSTIN, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD/BOULEVARD & CAUSEWAY FOR TOURISM ALONG SAN JOSE PORT, ROMBLON

Region IV-B, Region IV-B

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Dubduban Flood Control Structure, San Agustin, Tablas Island Romblon

ALCANTARA (ROMBLON), ROMBLON, Region IV-B

2023₱289.5M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG MONGPONG, BRGY. STA. LUCIA, SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. CENTRAL-BRGY. SAN AGUSTIN, STA. 000+240-STA. 000+735.5 (LEFT SIDE), SAN JOSE, OCC. MIND

Region IV-B, Region IV-B

2025₱284.2M
Past target date (DPWH On-Going)
View all 1,112 projects →

4. Implementation

Contract Amount

₱46,451,465.16

Progress

Reported complete (DPWH)

Start Date

February 27, 2020

Target End

March 28, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.