Roads18IK0063

REMOVAL OF LANDSLIDE, FILLING OF COMMON BORROW/BOULDERS ON DAMAGED ROAD & CONST. OF TEMPORARY DETOUR ALONG DAANG MAHARLIKA, BRGY. SILAGA, CATBALOGAN-BRGY. TOMINAMOS, STA. RITA, SAMAR, KO793+120-KO872+695 (INTERMITTENT SECTION)

REMOVAL OF LANDSLIDE, FILLING OF COMMON BORROW/BOULDERS ON DAMAGED ROAD & CONST. OF TEMPORARY DETOUR ALONG DAANG MAHARLIKA, BRGY. SILAGA, CATBALOGAN-BRGY. TOMINAMOS, STA. RITA, SAMAR, KO793+120-KO872+695 (INTERMITTENT SECTION) is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱5,714,218.82. Status: Reported complete (DPWH). Contractor on record: FRD CONST. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Extension of Flood Control Structure, Silaga Bridge along Daang Maharlika, Brgy. Tulay, Sta. Rita, Samar
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0031970

₱171,788.00 · FY2018

Released to Eastern Samar District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

27 projects · ₱647.5M total · 0 flags

4. Implementation

Contract Amount

₱5,714,218.82

Progress

Reported complete (DPWH)

Start Date

June 18, 2018

Target End

July 17, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.