Roads24KF0068

CONCRETING OF BRGY. MABUHAY TO BRGY. CAPOCAO FMR, BRGY. MABUHAY AND BRGY. CAPOCAO, SULTAN NAGA DIMAPORO, LANAO DEL NORTE

CONCRETING OF BRGY. MABUHAY TO BRGY. CAPOCAO FMR, BRGY. MABUHAY AND BRGY. CAPOCAO, SULTAN NAGA DIMAPORO, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱32,799,179.19. Status: Reported complete (DPWH). Contractor on record: MOYA CONST. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Big Banisilon, Tangcal, Lanao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Lanao del Norte 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

47 projects · ₱686.4M total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING - PRIMARY ROADSMAHARLIKA HIGHWAY( MALABANG-DOBLESTON-TUKURAN RD) - K1969 + (-651) - K1969 + (-641), K1981 + 600 - K1981 + 742, K1981 + 767.70 - K1982 + 000, K1984 + 000 - K1984 + 1067, K1985 + 060 - K1985 + 300, K1989 + 305 - K1989 + 449,

Region X, Region X

2025₱80.0M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE ROAD FROM BRGY. CALUBE-BRGY. LANTAWAN, SND, LANAO DEL NORTE

Lanao del Norte 2nd DEO, Region X

2025₱43.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD FROM BRGY. PULANG YUTA - BRGY. CALUBE, SND, LANAO DEL NORTE

Lanao del Norte 2nd DEO, Region X

2025₱39.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CLUSTER D OFF CARRAIGEWAY IMPROVEMENT OF VARIOUS ROAD PROJECTS IN LANAO DEL NORTE

Region X, Region X

2024₱34.2M
Reported complete (DPWH)
No sat.

ROAD WIDENING-PRIMARY ROADS MAHARLIKA HIGHWAY (MALABANG-DOBLESTON-TUKURAN RD) - K1980 + 969 - K1981 + 240, K1981 + 430 -K1981 + 608, K1981 + 875 - K1982 + 324

Region X, Region X

2025₱29.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITY, POBLACION, SULTAN NAGA DIMAPORO, LANAO DEL NORTE

Lanao del Norte 2nd DEO, Region X

2024₱29.4M
Reported complete (DPWH)
View all 47 projects →

4. Implementation

Contract Amount

₱32,799,179.19

Progress

Reported complete (DPWH)

Start Date

August 8, 2024

Target End

March 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.