Roads25DE0148

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BARANGAY P. NIOGAN - A

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BARANGAY P. NIOGAN - A is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱143,191,000.00. Status: Past target date (DPWH On-Going). Contractor on record: TCSC CORP. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Locloc, Bauan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

221 projects · ₱15.7B total · 0 flags

Other projects by this contractor

View all 221 projects →

4. Implementation

Contract Amount

₱143,191,000.00

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

November 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.