Roads18IG0028

NETWORK DEVELOPMENT - ROAD WIDENING-NATIONAL ROADS ALONG DAANG MAHARLIKA (LT) K0960+304-K0960+955, K0960+990-K0961+200,K0962+548-K0963+154

NETWORK DEVELOPMENT - ROAD WIDENING-NATIONAL ROADS ALONG DAANG MAHARLIKA (LT) K0960+304-K0960+955, K0960+990-K0961+200,K0962+548-K0963+154 is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱43,854,020.00. Status: Reported complete (DPWH). Contractor on record: REX E MORALES CONST. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Reconstruction/ of Kiga River Flood Control Structure at Kiga Bridge, K1055+706 along Ormoc-Baybay-Southern Leyte Boundary Road, Brgy. Sta. Cruz, Baybay City, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱43,854,020.00

Progress

Reported complete (DPWH)

Start Date

February 25, 2018

Target End

November 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.