Buildings and Facilities22HC0098

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY IMELDA, UBAY, BOHOL

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BARANGAY IMELDA, UBAY, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱4,802,490.00. Status: Reported complete (DPWH). Contractor on record: MLJ DIAZ BUILDERS INC. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Capayas Flood Control, Ubay, Bohol
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bohol 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

11 projects · ₱54.8M total · 0 flags

Other projects by this contractor

View all 11 projects →

4. Implementation

Contract Amount

₱4,802,490.00

Progress

Reported complete (DPWH)

Start Date

April 3, 2022

Target End

October 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.