Roads22DJ0054

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF DALAHICAN-MAYAO PARADA RO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF DALAHICAN-MAYAO PARADA RO is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱62,824,395.00. Status: Reported complete (DPWH). Contractor on record: ROMHEAD S J BUILDERS AND DEVELOPMENT INC. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2022 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22DJ0054 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-03-13 → 2020-08-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM:  SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF DALAHICAN-MAYAO PARADA RO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure, Barangay Poblacion 9, Lucena City, Quezon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Quezon 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

181 projects · ₱3.1B total · 0 flags

Other projects by this contractor

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF BANTILAN RIVER FLOOD CONTROL (PACKAGE 2), SARIAYA

Quezon 2nd DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL (PACKAGE 10), LUCENA CITY, QUEZON

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY (

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT LAGNAS RIVER (LAGNAS B

Quezon 2nd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY

Quezon 2nd DEO, Region IV-A

2025₱94.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD - K0232+379 - K0233+700, K0234+371 - K0236+ 850, K0237+789 - K0238+200

Quezon 3rd DEO, Region IV-A

2025₱93.6M
Past target date (DPWH On-Going)
View all 181 projects →

4. Implementation

Contract Amount

₱62,824,395.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

March 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.