Buildings and Facilities18GM0200

CONSTRUCTION OF ONE (1) UNIT THREE (3) STOREY TWELVE (12) CLASSROOMS AT GIL MONTILLA NATIONAL HIGH SCHOOL, SIPALAY CITY, NEGROS OCCIDENTAL

CONSTRUCTION OF ONE (1) UNIT THREE (3) STOREY TWELVE (12) CLASSROOMS AT GIL MONTILLA NATIONAL HIGH SCHOOL, SIPALAY CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 3rd DEO, Negros Island Region. Reported contract value: ₱30,144,672.16. Status: Reported complete (DPWH). Contractor on record: H L J CONST. Figures trace to dpwh.

Negros Occidental 3rd DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱40,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXII-18-0035169 · ₱8,084,089 · release to the district office, not itemized per project

    Possible match · score 0.71

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18GM0200 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-05-19 → 2020-02-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,512,056 per classroom= 1.8x the Negros Island Region median (n=274)

Contract cost ₱30,144,672 ÷ 12 classroom read from the DPWH title (“TWELVE (12) CLASSROOMS”; classroom count in title). National percentile: 82. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ONE (1) UNIT THREE (3) STOREY TWELVE (12) CLASSROOMS AT GIL MONTILLA NATIONAL HIGH SCHOOL, SIPALAY CITY, NEGROS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Lag-asan River (bothstream) along Bacolod North Road (S00406NR), Cadiz City, Negros Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-18-0035169

₱8,084,089.00 · FY2018

Released to Sultan Kudarat State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

274 projects · ₱4.5B total · 0 flags

4. Implementation

Contract Amount

₱30,144,672.16

Progress

Reported complete (DPWH)

Start Date

September 17, 2018

Target End

March 30, 2019

5. Audit