Buildings and Facilities17DH0019No coordinates published by DPWH

CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. SAN JOSE, STA. CRUZ, LAGUNA

CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. SAN JOSE, STA. CRUZ, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱4,536,944.52. Status: Reported complete (DPWH). Contractor on record: KLDS TRADING. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A

DPWH did not publish coordinates for this project. Location estimated from the project title (barangay level); satellite images may not show the exact site.

Region: Region IV-A

No before/after satellite images yet: DPWH did not publish coordinates, so imaging is queued for an ESTIMATED location derived from the project title. When processed, images will be labelled as an estimate and may not show the exact site.

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱20,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-17-0013804 · ₱130,490 · release to the district office, not itemized per project

    Possible match · score 0.67

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱4,536,945 · KLDS TRADING & CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. SAN JOSE, STA. CRUZ, LAGUNA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Maharlika Highway, Brgy. San Ignacio, San Pablo City K0084+850
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0013804

₱130,490.00 · FY2017

Released to Tarangnan National Sa High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Multi Purpose Covered Court, Brgy.

₱4,536,944.52 · KLDS TRADING & CONSTRUCTION

Award / contract ref: 17DH0019

Contractor

B

137 projects · ₱6.7B total · 0 flags

4. Implementation

Contract Amount

₱4,536,944.52

Progress

Reported complete (DPWH)

Start Date

February 9, 2017

Target End

June 8, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.