Buildings and Facilities18FC0176

CONSTRUCTION OF TWO (2) STOREY, FOUR (4) CLASSROOM SCHOOL BUILDING, DUMAGMANG INTEGRATED SCHOOL, LAB

CONSTRUCTION OF TWO (2) STOREY, FOUR (4) CLASSROOM SCHOOL BUILDING, DUMAGMANG INTEGRATED SCHOOL, LAB is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱10,153,473.36. Status: Reported complete (DPWH). Contractor on record: RUR CONST AND SUPPLY. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Talisay River Control, Phase 2, Talisay, Camarines Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,153,473.36

Progress

Reported complete (DPWH)

Start Date

March 28, 2019

Target End

July 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.