Buildings and Facilities18DM0118

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING AT ILAYANG YUNI NHS

CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING AT ILAYANG YUNI NHS is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱12,089,250.00. Status: Reported complete (DPWH). Contractor on record: R T Y CONST. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱40,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0032863 · · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱11,847,095 · R.T.Y. CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-02-26 → 2025-01-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING AT ILAYANG YUNI NHS

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Catanauan River (Downstream Section), Catanauan, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Two(2)-Storey Four(4)-Classroom Sc

₱11,847,094.91 · R.T.Y. CONSTRUCTION

Award / contract ref: 18DM0118

Contractor

A

177 projects · ₱6.4B total · 4 flags

Other projects by this contractor

No sat.

MFO-1 NATIONAL ROAD NETWORK SERVICES NETWORK DEVELOPMENT CONSTRUCTION OF BY-PASSES/DIVERSION ROADS INCL. ROW LOPEZ BY-PASS ROAD, INCL. ROW, QUEZON

Region IV-A, Region IV-A

2017₱145.9M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (CONCRETE PAVING) ALONG SAN FRANCISCO-SAN ANDRES-SAN NARCISO ROAD, K0318+216-K0321+966

Quezon 3rd DEO, Region IV-A

2016₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL STRATEGIES TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0272+067-K0275+840, BUENAVISTA, QUEZON

Region IV-A, Region IV-A

2017₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG CATANAUAN-BUENAVISTA ROAD, K0262+323-K0266+025, BUENAVISTA, QUEZON

Region IV-A, Region IV-A

2017₱144.7M
Reported complete (DPWH)
No sat.

FY 2018 DPWH INFRASTRUCTURE PROGRAM, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM, ROAD WIDENING/PRIMARY ROADS, DAANG MAHARLIKA (LZ) K0192+100.00-K0192+729.00, K0201+730-K0203+839.00, QUEZON

Region IV-A, Region IV-A

2018₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALONG MSR JCT-LOPEZ-CATANAUAN ROAD, K0248+912-K0250+790 & K0250+816-K0254+275, CATANAUAN, QUEZON

Region IV-A, Region IV-A

2017₱144.3M
Reported complete (DPWH)
View all 177 projects →

4. Implementation

Contract Amount

₱12,089,250.00

Progress

Reported complete (DPWH)

Start Date

November 29, 2018

Target End

July 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.