Construction of Flood Mitigation Structure22DE0091

Construction of Flood Control Structure, Poblacion, San Luis, Batangas

Construction of Flood Control Structure, Poblacion, San Luis, Batangas is a DPWH-tracked public work in SAN LUIS (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱78,404,898.22. Status: Reported complete (DPWH). Contractor on record: TCSC CORP. Figures trace to sumbong.

SAN LUIS (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Brgy. Solo, Mabini, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002894

₱805,017,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002638

₱178,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0006533

₱40,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001716

₱20,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002774

₱18,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

221 projects · ₱15.7B total · 0 flags

Other projects by this contractor

View all 221 projects →

4. Implementation

Contract Amount

₱78,404,898.22

Progress

Reported complete (DPWH)

Start Date

March 31, 2022

Target End

January 24, 2023