Roads23NC0060

INSTALLATION OF LED SOLAR STREET LIGHTS AT PUROK 1 TO PUROK 5 BRGY. PASTA, SAN FRANCISCO, AGUSAN DEL SUR

INSTALLATION OF LED SOLAR STREET LIGHTS AT PUROK 1 TO PUROK 5 BRGY. PASTA, SAN FRANCISCO, AGUSAN DEL SUR is a DPWH-tracked public work in Agusan del Sur 2nd DEO, Region XIII. Reported contract value: ₱4,676,478.95. Status: Reported complete (DPWH). Contractor on record: DBR CONST CORP FORMERLY: D B RAVELO CONST. Figures trace to dpwh.

Agusan del Sur 2nd DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Mitigation along Adlayan River Bank (Downstream) San Francisco, Agusan Del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Agusan del Sur 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,676,478.95

Progress

Reported complete (DPWH)

Start Date

July 14, 2023

Target End

November 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.