Roads15FI0130

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE ALONG JCT. CROSSING-MANDAON ROAD, K0046+(-375) - K004

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE ALONG JCT. CROSSING-MANDAON ROAD, K0046+(-375) - K004 is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱31,788,045.30. Status: Reported complete (DPWH). Contractor on record: CL CARANDANG CONST AND SUPPLY CORP FORMERLY: CL CARANDANG ENT. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2016 · ₱15,835 (shared by many projects, not this project's own line)

    Possible match · score 0.71

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-16-0038868 · · release to the district office, not itemized per project

    Possible match · score 0.64

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 15FI0130 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2013-03-30 → 2019-03-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE ALONG JCT. CROSSING-MANDAON ROAD, K0046+(-375) - K004

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 71%

UACS
18001
Amount
₱15,835,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures/Slope Protection, Talisay River, Sta 0+000 - Sta 0+805, Maluya - Cupang, Balanga City, Bataan
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038868

₱-39,928,474.00 · FY2016

Released to Northern Sa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

194 projects · ₱2.4B total · 0 flags

Other projects by this contractor

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SAN RAMON RIVER, USON, MASBATE

Masbate 3rd DEO, Region V

2024₱96.4M
Reported complete (100% progress, DPWH status On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATUILA RIVER, BALENO, MA

Masbate 2nd DEO, Region V

2025₱85.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT- ROAD WIDENING- SECONDARY ROADS, MASBATE- CATAINGAN- PLACER ROAD, K0070+485- K0072+870

Masbate 3rd DEO, Region V

2019₱67.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION-CONSTRUCTION OF MASBATE CITY PORT-COASTAL ROAD (DIVERSION ROAD). MASBATE CITY, MASBATE

Masbate 2nd DEO, Region V

2022₱64.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS - BALUD - PALANI - PANUBIGAN - PAJO - TALISAY ROAD LEADING TO PALANI BEACHES, PANUBIGAN, PAJO AND TALISAY MANGROVE AREA, BRGY. TALIS

Masbate 2nd DEO, Region V

2020₱61.6M
Reported complete (DPWH)
No sat.

ROAD WIDENING - ALONG MINDORO WEST COASTAL RD ( S00095MR) K0231+556 - K0233+216, SAN JOSE, OCC. MINDORO

Mindoro Occidental DEO, Region IV-B

2019₱49.0M
Reported complete (DPWH)
View all 194 projects →

4. Implementation

Contract Amount

₱31,788,045.30

Progress

Reported complete (DPWH)

Start Date

March 22, 2016

Target End

July 25, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.