Buildings and Facilities20GB0128

CONSTRUCTION OF 2 UNITS 1 STOREY TWO (2) CLASSROOM SCHOOL BUILDING AT APONG ELEMENTARY SCHOOL SIBALO

CONSTRUCTION OF 2 UNITS 1 STOREY TWO (2) CLASSROOM SCHOOL BUILDING AT APONG ELEMENTARY SCHOOL SIBALO is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱9,783,831.41. Status: Reported complete (DPWH). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to dpwh.

Antique DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱4,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay San Pedro, San Jose de Buenavista, Antique
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Antique DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20GB0128 - Construction of 2 Units 1 Storey Two (2

₱9,783,831.41 · GREAT PACIFIC BUILDERS AND GEN. CONTRACTOR .

Contractor

B

296 projects · ₱11.9B total · 3 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. ALAS-ASI-IPAG, MARIVELES, BATAAN (PACKAGE 1),

Region III, Region III

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353

Region IV-A, Region IV-A

2024₱244.0M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR

Region IV-B, Region IV-B

2024₱234.3M
Past target date (DPWH On-Going)
View all 296 projects →

4. Implementation

Contract Amount

₱9,783,831.41

Progress

Reported complete (DPWH)

Start Date

August 28, 2020

Target End

August 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.