Construction of Revetment23E00150

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro is a DPWH-tracked public work in SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B. Reported contract value: ₱241,246,839.20. Status: Reported complete (DPWH). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to sumbong.

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Patrick River, Barangay Tagumpay Section, Sta. 0+000 - Sta. 0+440, Sablayan, Occidental Mindoro
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Mindoro Occidental District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

296 projects · ₱11.9B total · 3 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. ALAS-ASI-IPAG, MARIVELES, BATAAN (PACKAGE 1),

Region III, Region III

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353

Region IV-A, Region IV-A

2024₱244.0M
Past target date (DPWH On-Going)

Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR

Region IV-B, Region IV-B

2024₱234.3M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO

Region IV-B, Region IV-B

2023₱221.9M
Past target date (DPWH On-Going)
View all 296 projects →

4. Implementation

Contract Amount

₱241,246,839.20

Progress

Reported complete (DPWH)

Start Date

April 13, 2023

Target End

April 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.