Roads24D00109

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS DAANG MAHARLIKA (LZ) - K0078 + 722 - K0079 + 366, K0090 + 042 - K0090 + 663, K0090 + 956 - K0091 + 353 is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱243,992,944.44. Status: Past target date (DPWH On-Going). Contractor on record: GREAT PACIFIC BUILDERS AND GEN CONTRACTOR INC. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

296 projects · ₱11.9B total · 3 flags

Other projects by this contractor

No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FR. THE NAT'L. ROAD/S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, BRGY. ALAS-ASI-IPAG, MARIVELES, BATAAN (PACKAGE 1),

Region III, Region III

2023₱289.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure (River Training Works) along Mompong River (Downstream), Sablayan, Occidental Mindoro

SABLAYAN (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2024₱289.5M
Reported complete (DPWH)

Construction of Shore Protection and Coastal Road Development along Barangay Poblacion 2, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

Construction of Road Dike/Esplanade along Pangalaan River (Right Side), Naujan, Oriental Mindoro

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B

2024₱241.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 2, BRGY. SAN LUIS, NAUJAN, OR. MINDOR

Region IV-B, Region IV-B

2024₱234.3M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF ROXAS BY-PASS ROAD, ROXAS, OR. MINDORO

Region IV-B, Region IV-B

2023₱221.9M
Past target date (DPWH On-Going)
View all 296 projects →

4. Implementation

Contract Amount

₱243,992,944.44

Progress

Past target date (DPWH On-Going)

Start Date

April 18, 2024

Target End

February 11, 2025

5. Audit