CONSTRUCTION OF BYPASS (ALTERNATE) ROAD (PHASE V), BARANGAY MUZON, SAN JOSE DEL MONTE CITY, BULACAN

CONSTRUCTION OF BYPASS (ALTERNATE) ROAD (PHASE V), BARANGAY MUZON, SAN JOSE DEL MONTE CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱95,038,795.96. Status: Reported complete (DPWH). Contractor on record: ROYAL CROWN MONARCH CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Gaya - gaya, San Jose del Monte City, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

328 projects · ₱20.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF PAMPANGA

Region III, Region III

2023₱228.7M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, MANGATAREM-STA CRUZ ROAD, PACKAGE 2, PANGASINAN

Region I, Region I

2018₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS AND DECLARED TOURISM DESTINATIONS, CONCRETING OF ROAD FROM LINGAYEN BAYWALK TO BINMALEY, PANGASINAN

Region I, Region I

2016₱185.6M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 2, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 3, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2024₱140.4M
Past target date (DPWH On-Going)
View all 328 projects →

4. Implementation

Contract Amount

₱95,038,795.96

Progress

Reported complete (DPWH)

Start Date

April 25, 2024

Target End

June 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.