Buildings and Facilities25GG0091

CONSTRUCTION OF MULTI - PURPOSE BUILDING, PHASE II, SAN ENRIQUE, ILOILO

CONSTRUCTION OF MULTI - PURPOSE BUILDING, PHASE II, SAN ENRIQUE, ILOILO is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱4,982,598.51. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: CONTE BUILDERS. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Slope Protection in Barotac Nuevo, Iloilo
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Iloilo 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,982,598.51

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 6, 2025

Target End

July 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.