GAA 2025 OO-225KG0012

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MAIGO BRIDGE (BO0949MN), PACKAGE 1, MAIGO, LANAO DEL NORTE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MAIGO BRIDGE (BO0949MN), PACKAGE 1, MAIGO, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱48,402,023.16. Status: Past target date (DPWH On-Going). Contractor on record: LANAO BUILDER AND ENT. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Maigo Bridge (B00949MN), Package 1, Maigo, Lanao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,402,023.16

Progress

Past target date (DPWH On-Going)

Start Date

March 19, 2025

Target End

January 30, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.