Roads17AB0001

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, BATAC-ESPIRITU (BANNA) ROAD, K0471+391 - K0472+928

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, BATAC-ESPIRITU (BANNA) ROAD, K0471+391 - K0472+928 is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱19,599,987.80. Status: Reported complete (DPWH). Contractor on record: AJ TAYLAN CONST CORP. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Dongdong River, Brgy. Acnam, Nueva Era, Ilocos Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0016719

₱476,520.00 · FY2017

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

48 projects · ₱1.3B total · 0 flags

Other projects by this contractor

View all 48 projects →

4. Implementation

Contract Amount

₱19,599,987.80

Progress

Reported complete (DPWH)

Start Date

February 17, 2017

Target End

August 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.