Buildings and Facilities25AI0138

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CRISIS MANAGEMENT CENTER) BARANGAY CARMAY EAST, ROSALES, PANGASINAN

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CRISIS MANAGEMENT CENTER) BARANGAY CARMAY EAST, ROSALES, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱28,808,245.10. Status: Past target date (DPWH On-Going). Contractor on record: RIVBROS CONST FACTORS. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabalancian River and Allied Rivers Flood Mitigation Structure, Rosales, Pangasinan (Package A)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Pangasinan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,808,245.10

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

January 21, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.