ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0462+500-K0462+508, K0464+238-K0464+2
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS, ABRA-KALINGA ROAD-K0462+500-K0462+508, K0464+238-K0464+2 is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱8,707,972.74. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: 739 BUILDERS. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost