Roads21M00049

ROAD WIDENING SURALLAH-TBOLI-SAN JOSE ROAD (GEN. SANTOS CITY), PACKAGE A, STA. 18+970-STA. 21+430, TBOLI, SOUTH COTABATO

ROAD WIDENING SURALLAH-TBOLI-SAN JOSE ROAD (GEN. SANTOS CITY), PACKAGE A, STA. 18+970-STA. 21+430, TBOLI, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱106,148,956.60. Status: Reported complete (DPWH). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

407 projects · ₱34.7B total · 2 flags

4. Implementation

Contract Amount

₱106,148,956.60

Progress

Reported complete (DPWH)

Start Date

August 25, 2021

Target End

December 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.