Flood Control and Drainage18A00135

REHABILITATION OF FLOOD CONTROL AND DRAINAGE STRUCTURES ALONG ABRA RIVER, SANTA, ILOCOS SUR

REHABILITATION OF FLOOD CONTROL AND DRAINAGE STRUCTURES ALONG ABRA RIVER, SANTA, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱8,457,282.33. Status: Reported complete (DPWH). Contractor on record: M G LUALHATI CONST CORP. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,457,282.33

Progress

Reported complete (DPWH)

Start Date

March 19, 2019

Target End

May 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.