Flood Control and Drainage17HI0036

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG CEBU NORTH HAGNAYA WHARF ROAD, DANAO CITY, CEBU (K0035+800 - K0036+542)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL ALONG CEBU NORTH HAGNAYA WHARF ROAD, DANAO CITY, CEBU (K0035+800 - K0036+542) is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱18,382,594.42. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control North Hagnaya Wharf Road, K0035+800-K0036+542, Danao City, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0022755

₱2,108,129.00 · FY2017

Released to Philippine Air For ( Air Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱18,382,594.42

Progress

Reported complete (DPWH)

Start Date

March 6, 2017

Target End

October 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.